Romania Switches On Its Largest New Wind Farm in More Than a Decade, Adding 192 MW

Rezolv Energy has switched on the first phase of its VIFOR wind farm in Buzău County, 30 Vestas turbines producing 192 MW, the largest wind project brought online in Romania in more than a decade.

By , Editor

· Updated · 2 min read

Source: Rezolv Energy ↗
Share
Wind turbines standing in a grassy field
Wind turbines standing in a grassy field. Photo: EdWhiteImages (Pixabay)

Rezolv Energy switched on the first phase of its VIFOR wind farm in Buzău County, Romania, on 2 October, adding 192 MW of capacity that the company says makes it the largest new wind project in the country in more than a decade, according to a Rezolv Energy announcement.

Thirty turbines, each rated at 6.4 MW

Phase one has 30 Vestas EnVentus V162 turbines of 6.4 MW each, with 166-meter towers and 162-meter rotors, according to the Diplomat Bucharest. Vestas also built the project as its engineering, procurement and construction partner.

Rezolv estimates that once fully running, VIFOR will power more than 270,000 homes and avoid about 540,000 tonnes of CO₂-equivalent emissions a year. Both figures are company estimates.

Romania's wind buildout had stalled for a decade

Romania built most of its wind capacity between 2010 and 2015, after which growth stalled, according to Rezolv. The country now has just over 3 GW of wind installed, while its National Energy and Climate Plan targets 7.3 GW by 2030. Projects like VIFOR are part of closing that gap.

Financing and corporate buyers lined up in advance

Eight lenders, led by Erste Group, UniCredit and the European Bank for Reconstruction and Development, provided up to €291 million for phase one, and up to €331 million has been arranged for phase two. Six corporate power purchase agreements, with T-Mobile Czech Republic, Slovak Telekom, CE Colo Czech Republic, Bekaert, A2A and Etem Gestamp, cover more than 350 GWh a year, so part of the output is already sold.

Birds, bats and a second phase in 2027

The site overlaps two Natura 2000 protected areas, and Rezolv says it has a biodiversity management plan with bird and bat monitoring. Phase two is scheduled for completion in 2027 and would bring VIFOR's total capacity to 461 MW, which would make it one of the largest onshore wind farms in Europe.

Rezolv CEO Alastair Hammond said the company "was established to be a leader of the energy transition across Southeastern Europe." Jaroslava Korpanec, head of Central and Eastern Europe infrastructure at investor Actis, said Rezolv "has moved from developer to operator at pace." The company, also backed by Mubadala, opened its first project, a 225 MW solar park in Bulgaria, in May.

The capacity, household and emissions figures come from the developer and have not been independently verified. For wind farms near bird habitat, a simple fix has been tested in Spain: painting one turbine blade black cut bird deaths by 74%.

Sources

How we choose and verify sources: editorial policy.

More stories: Clean energy progress (15) →

Your weekly dose of good news

The 5 biggest positive stories of the week, straight to your inbox. Free, no noise.